Electric Control System for GN 500GPM mud recycling system

GN 500GPM mud recycling system is the most popular size for different kind of trenchless activities, like horizontal directional drilling (HDD), coal bed methane (CBM), water well drilling, and small size workover rigs.

GN Solids Control makes GN 500GPM mud recycling system. The system is equipped with 1 ea shale shaker, 1 eadesilter mud cleaner. But do you know how to operate the system?drilling mud system

Below is the Operation Instruction for Electric Control system of GN 500GPM mud recycling system.

1. Connect the main power source; turn on power source switch of system electric control cabinet, working voltage shown on voltmeter.

2. Press 1# Sand Pump start button when start it. 1# Sand Pump is startedwhile indicator light for 1# Sand Pump Operation is on and 1# Sand Pump start to run.  Press 1# Sand Pump stop button when stop it. 1# Sand Pump is stopped while indicator light is off and pump stops.

3. Press 2# Sand Pump start button when start it. 2# Sand Pump is started while indicator light for 2# Sand Pump Operation is on and 2# Sand Pump start to run.  Press 2# Sand Pump stop button when stop it. 2# Sand Pump is stopped while indicator light is off and pump stops.

4. Press Mud Agitator start button when start it. Mud Agitator is started while indicate light for Mud Agitator Operation is on and Mud Agitator start to run.  Press Mud Agitator stop button when stop it. Mud Agitator is stopped while indicate light is off and Mud Agitator stops.

5. Press Submersible Pump start button when start it. Submersible Pump is started while indicate light for Submersible Pump Operation is on and Submersible Pump start to run.  Press Submersible Pump stop button when stop it. Submersible Pump is stopped while indicate light is off and Submersible Pump stops.

6. Press Shale Shaker start button when start it. Shale Shaker is started while indicate light for Shale Shaker Operation is on and Shale Shaker start to run.  Press Shale Shaker stop button when stop it. Shale Shaker is stopped while indicate light is off and Shaker stops.

7. Press Mud Cleaner start button when start it. Mud Cleaner is started while indicate light for Mud Cleaner Operation is on and Mud Cleaner start to run. Press Mud Cleaner stop button when stop it. Mud Cleaner is stopped while indicate light is off and Mud Cleaner stops